On Tue, Apr 22, 2014 at 05:06:33AM -0400, Jaroslav Reznik wrote:
> Cutting one week from Alpha/Beta cycle is doable but only when it's
> really, really needed. We did this voodoo magic a few times to avoid
> Christmas etc. and believe me - that note in the Task Juggler source
> for schedule - never, ever, do this - is just truth. It pains.

And in practice, it's probably a lie -- those cut weeks get added back as
delays later, so it's really just shuffling numbers around for extra work
and no benefit.


-- 
Matthew Miller    --   Fedora Project    --    <mattdm at fedoraproject.org>
                                  "Tepid change for the somewhat better!"