Change Request: bodhi-0.7.7

Mike McGrath mmcgrath at redhat.com
Wed Aug 4 03:18:05 UTC 2010


On Tue, 3 Aug 2010, Luke Macken wrote:

> Hey guys,
>
> I want to perform a production bodhi upgrade.
>
> Risks are fairly minimal.  I've written unit tests for the new major
> features,
> and have been bashing on this code in staging all day today.  I also tested
> `yum downgrade bodhi-server` in staging, which works fine.  There are no
> database schema changes.
>
> The current version of bodhi in production slipped out of staging a week
> or so ago, so a lot of these changes are already in production.  This
> newer release fixes a few issues, and now adheres to the
> minimum-time-in-testing part of the package update acceptance criteria.
>
> Changes in this release include:
>

+1, I assume if things go south we can just downgrade right?

	-Mike


More information about the infrastructure mailing list