Greetings,

Representatives from Fedora QA, Rel-Eng and Development met on IRC to
review whether the Fedora 13 Beta release criteria [1] have been met.
The team agreed that the Beta criteria have not been met, and to slip in
the F-13 schedule by one week.  For additional details, please refer to
the attached minutes.

Thanks,
James

[1] https://fedoraproject.org/wiki/Fedora_13_Beta_Release_Criteria
-------------- next part --------------
========================================================
#fedora-meeting: F-13-Beta engineering readiness meeting
========================================================


Meeting started by jlaska at 00:03:18 UTC. The full logs are available
at
http://meetbot.fedoraproject.org/fedora-meeting/2010-04-01/f-13-beta-eng-readiness.2010-04-01-00.03.log.html
.



Meeting summary
---------------
* Waiting for critical mass ...  (jlaska, 00:03:32)

* Why are we here?  (jlaska, 00:05:57)
  * The purpose is to decide whether the beta has met the release
    criteria  (jlaska, 00:06:05)
  * LINK: https://fedoraproject.org/wiki/Fedora_13_Beta_Release_Criteria
    (jlaska, 00:06:29)
  * Oxf13 representing release engineering  (jlaska, 00:06:59)
  * adamw representing QA  (jlaska, 00:07:07)
  * ______ representing devel  (jlaska, 00:08:03)

* Go or No Go?  (jlaska, 00:08:26)
  * IDEA: test case idea - create a test repo with intentionally broken
    deps  (jlaska, 00:11:56)
  * AGREED: not enough information known about bug#578633 failure
    conditions  (jlaska, 00:36:47)
  * AGREED: Beta release criteria have not been met, 1 week slip for
    F-13-Beta  (jlaska, 00:39:31)

* What's next?  (jlaska, 00:42:27)
  * ACTION: poelcat will update schedule with 1 week slip  (jlaska,
    00:43:30)
  * ACTION: Oxf13 will post slip announcement  (jlaska, 00:44:11)
  * New go/no_go meeting @ 2010-04-08 20:00 EDT  (jlaska, 00:44:35)
  * LINK:
    https://fedoraproject.org/wiki/Releases/13/Schedule#Key_Milestones
    reflects new dates  (poelcat, 00:47:15)

Meeting ended at 00:48:45 UTC.




Action Items
------------
* poelcat will update schedule with 1 week slip
* Oxf13 will post slip announcement




Action Items, by person
-----------------------
* Oxf13
  * Oxf13 will post slip announcement
* poelcat
  * poelcat will update schedule with 1 week slip
* **UNASSIGNED**
  * (none)




People Present (lines said)
---------------------------
* jlaska (91)
* adamw (45)
* Oxf13 (43)
* halfline (17)
* poelcat (13)
* zodbot (7)
* wwoods (7)
* stickster (2)
* brunowolff (2)




Generated by `MeetBot`_ 0.1.4

.. _`MeetBot`: http://wiki.debian.org/MeetBot
-------------- next part --------------
A non-text attachment was scrubbed...
Name: not available
Type: application/pgp-signature
Size: 198 bytes
Desc: This is a digitally signed message part
Url : http://lists.fedoraproject.org/pipermail/test/attachments/20100331/b7023bdb/attachment.bin 


More information about the test mailing list