F-13 Pre-RC Acceptance Test Run Recap
Adam Williamson
awilliam at redhat.com
Wed Apr 28 00:48:48 UTC 2010
On Tue, 2010-04-27 at 19:57 -0400, James Laska wrote:
> > Should we have a provision to re-run the acceptance testing if the
> > initial run fails, after the issue which caused the initial failure is
> > fixed? The current procedure would seem to allow us to catch one, and
> > only one, failure-causing bug: if there's another one behind it in the
> > install process, we won't catch that.
>
> Good suggestion. These milestones were originally intended to make sure
> someone was looking at the results leading up to the 'test compose'.
> The good news ... the acceptance tests run whenever the repo and install
> images change in both Branched and Rawhide. I'll check in on the
> results leading up to this weeks RC 'test compose' milestone.
Aha, I see - thanks.
--
Adam Williamson
Fedora QA Community Monkey
IRC: adamw | Fedora Talk: adamwill AT fedoraproject DOT org
http://www.happyassassin.net
More information about the test
mailing list