Dne 27. 09. 19 v 23:55 Kevin Fenzi napsal(a):
* Populate the new datacenter with new hardware to replace old
hardware that
either wouldn’t survive the shipping or is due to be refreshed
In past, I was in touch with people working in datacenters and they moved several
companies from one datacenter to
another one.
They claimed that during this transport there was non trivial number of servers which did
not survive the shipping.
I do not recall the number. It may be worth to ask some people who done similar migration
in past and get those numbers.
IIRC it was "small percent" (~1-2%).
And get pre-approved CAPEX for that. And some spare server as temporary replacement if
something crucial dies.
--
Miroslav Suchy, RHCA
Red Hat, Associate Manager ABRT/Copr, #brno, #fedora-buildsys