#fedora-meeting: F-13-Alpha engineering readiness meeting
=========================================================
Meeting started by jlaska at 18:59:18 UTC. The full logs are available
at
http://meetbot.fedoraproject.org/fedora-meeting/2010-02-25/fedora-meeting...
.
Meeting summary
---------------
* gathering devel, rel-eng and qa reps (jlaska, 18:59:40)
* intro (jlaska, 19:06:24)
* The purpose is to decide whether the alpha has met the release
criteria (jlaska, 19:07:38)
* LINK:
https://fedoraproject.org/wiki/Fedora_13_Alpha_Release_Criteria
(jlaska, 19:07:56)
* Go or No Go (jlaska, 19:09:02)
* traditional x86-64 install is broken (bug#568235) (jlaska,
19:11:39)
* live install is broken (bug#565840) (jlaska, 19:11:44)
* installing updates is broken (bug#568193 bug#567346) (jlaska,
19:12:12)
* QA votes 'no go' - citing additional testing against remaining
F13Alpha blockers and walking the Alpha test matrix (jlaska,
19:31:42)
* Rel-Eng votes 'no go' - reluctant considering how close we are and
that the next RC will likely be the final (jlaska, 19:32:28)
* Devel votes 'no go' - notting cited the current data and matrix
results, dcbw cited importance of installing (jlaska, 19:34:26)
* contingency plan (jlaska, 19:41:15)
*
https://fedoraproject.org/wiki/Engineering_Readiness_Meetings#Contingency...
indicates a 1 week slip as a contingency plan (jlaska, 19:41:35)
* Oxf13 notes that with No Frozen Rawhide (NFR), we no longer have the
pressure valves from previous releases. Developing (rawhide) and
testing (f-13-updates-testing) can continue (jlaska, 19:52:32)
* IDEA: Do not slip Beta/Final milestone dates, due to NFR not
shorting developers on development time. (Oxf13, 19:53:26)
* AGREED: decided to absorb the slip and not move the F-13 release out
by one week (future slips may incur a cost) (jlaska, 19:58:30)
* ACTION: Oxf13 will announce the slip to (devel-)announce (Oxf13,
19:59:50)
* ACTION: stickster will update schedule pages and poke poelcat about
TJ (Oxf13, 20:00:42)
* ACTION: stickster will re-schedule release readiness meeting
(Oxf13, 20:01:25)
* ACTION: QA - continue testing RC4 when available and verifying
remaining F13Alpha bugs (jlaska, 20:04:04)
Meeting ended at 20:05:09 UTC.
Action Items
------------
* Oxf13 will announce the slip to (devel-)announce
* stickster will update schedule pages and poke poelcat about TJ
* stickster will re-schedule release readiness meeting
* QA - continue testing RC4 when available and verifying remaining
F13Alpha bugs
Action Items, by person
-----------------------
* Oxf13
* Oxf13 will announce the slip to (devel-)announce
* stickster
* stickster will update schedule pages and poke poelcat about TJ
* stickster will re-schedule release readiness meeting
* **UNASSIGNED**
* QA - continue testing RC4 when available and verifying remaining
F13Alpha bugs
People Present (lines said)
---------------------------
* jlaska (102)
* Oxf13 (86)
* stickster (39)
* adamw (24)
* ajax (7)
* dlehman (5)
* zodbot (5)
* dcbw (4)
* notting (3)
* nirik (2)
* clumens (1)
* mchua (1)
Generated by `MeetBot`_ 0.1.4
.. _`MeetBot`:
http://wiki.debian.org/MeetBot