On Mon, Jan 14, 2019 at 12:45 AM Sumantro Mukherjee <sumukher(a)redhat.com> wrote:
Usually 2-3 weeks after the GA, we tend to go ahead and call for test
days
which is an email going out to all the teams and subteams notfing that we will
are accepting test day tickets for the upcoming release cycle.
We do have some fixed set of test day like GNOME, i18n , Cloud, Modularity, Upgrade
which run at different points in time from pre-beta to final accompanied with
the new changeset which needs testing.
We also have Kernel Test Day which is not realese bound and happens whever a new
Kernel releases which is every 8-10 weeks. The 'Create Test Days' can start off
after the Call for test days email is sent out and end about 2 weeks before the rain
date.
Let me make sure I understand what you're saying. You want "Call for
test days" to start earlier in the cycle and the create test days task
to run until just before GA? So for example, if this was already
changed for F30, the timeline would look like this:
2018-10-23 Preferred F29 GA target
2018-10-30 Alternate F29 GA target
2018-11-20 Call for F30 test days
2018-11-27 Create F30 test days (start)
2019-04-23 Create F30 test days (end)
If that's not correct, can you please update my example timeline above?
Thanks,
BC
--
Ben Cotton
Fedora Program Manager
TZ=America/Indiana/Indianapolis