Start End Name
Wed 18-Nov Tue 04-May Translate All Guides (POT to PO)
Thu 11-Mar Mon 05-Apr Translate Beta Release Notes
Mon 15-Mar Mon 22-Mar Review and correct Beta Release Notes (daily
buids html)
Tue 16-Mar Tue 23-Mar Software: Rebuild all translated packages
Mon 22-Mar Mon 22-Mar Translation Deadline: Beta Release Notes (PO
Files complete)
Mon 22-Mar Wed 24-Mar Build fed-rel-notes.rpm for Beta Release
Tue 23-Mar Tue 23-Mar Development: Beta Freeze--Features 100%
Tue 23-Mar Mon 26-Apr Translate Final Release Notes (POT to PO)
Thu 01-Apr Thu 01-Apr Beta Project Wide Release Readiness Meeting
Tue 06-Apr Tue 06-Apr Beta Release Public Availability
Tue 06-Apr Tue 06-Apr Reminder to f-websites-list about POT/PO dates
in 7 days