Ankitkumar Rameshchandra Patel said the following on 08/14/2009 11:54 PM
Pacific Time:
John Poelstra wrote:
> Not quite sure how to proceed....
>
> Right now we have:
>
> 6. Final Software Translation Period (POT to PO) Tue 2009-08-04 to
> Thu 2009-09-03
> 7. Review Software Translations Thu 2009-09-03 to
> Tue 2009-09-15 8. Ongoing Test Package Builds for Translation
> Review Thu 2009-09-03 to Tue 2009-09-15
>
> They all depend on each other and follow one right after the other.
> Can you propose new dates for 6, 7, 8 and so that is still the case?
w.r.t.
http://poelstra.fedorapeople.org/schedules/f-12/f-12-trans-tasks.html
6. Final Software Translation Period (POT to PO) Tue 2009-08-04 to Thu
2009-09-03
7. Ongoing Test Package Builds for Translation Review Thu 2009-09-03
to Tue 2009-09-07
8. Review Software Translations Thu 2009-09-08 to Tue
2009-09-15
Is above change looks correct & possible now?
Yes. Changes made and should be live now.
John